tangxinwei2008(威望:3)
(广东 深圳)
在校学生 工程师
- 十年SQE, 现转岗NPI QE
赞同来自:
仅供参考:
--------------------
AUDIT AGENDA
Key Audit Points:
Process control critical areas including:
a. Equipment parameters control
b. Control plan
c. Inspection process
d. Silkscreen marking process
e. Product packaging design and quality control
2 个回复
tangxinwei2008 (威望:3) (广东 深圳) 在校学生 工程师 - 十年SQE, 现转岗NPI QE
赞同来自:
--------------------
AUDIT AGENDA
Process control critical areas including:
a. Equipment parameters control
b. Control plan
c. Inspection process
d. Silkscreen marking process
e. Product packaging design and quality control
Technical capability validation (tool/mold design)
Outgoing inspection system
- Inspection Report
- CoC
XXX Medical cover mechanical drawing requirements
Visual criteria correlation
Signed GAQ
- PRODUCT AUDIT
Visual CriteriaDimensions (tolerances)
Material Specifications
Defined IMI Requirement
- PROCESS AUDIT
Process Control PlanEquipment Parameters
Technology
其他:
AUDIT EXPECTATIONS
Assess system and process capability to meet XXXgeneral requirements
Validate technical capability to consistently meet XXXX Medical product requirements
Establish supplier/XXX partnership